I figure I have 4 days to go. 5 if I consider thursday, but im trying to reserve that for testing.
I have to do the following:
-mount motor (its just sitting on the rails currently)
-mount seat
-mount pedal assy
-mount gas tank
-wire gauges, ignition (using previous wire loom)
-run plumbing
-set up pump (ride plate/cradle, wedges, nozzle, steering)
after the fiasco with the balancer, i thought i was going to have to throw in the towel.....but this is starting to look very possible. The motor went in with a snap. I just dropped it in and it was dead nuts on. I didnt have to cut/shim at all.....dumb luck. Ralph and I spent hours dialing in a rail kit before.
If I really stuck to it, I could have all of the above done in 2 days. we'll see. ...just glad to see the light at the end of this tunnel finally.